Owner/Investor: Sibelco
Employer : Sibelco
• Project aims production of floated feldspar and glass grade feldspar in a new, modern plant with a capacity of 80 tph.
• New plant is of 3 main process units, crushing, washing and drying with subsidiary structures and utilities.
• Structures and system in the plant are :
Raw material dumping structure
Crushing plant crushers and screens area
Washing and flotation building
Drying building
Storage silos
Big bags warehouse
Thickener
Open stockpiles
Contaminated and non contaminated water basins
Feeding hopers
Electrical buildings
Warehouse
Office building
Water well stations
Truck weighbridges
Truck loading areas
Belt conveyors
• Scope of work
All engineering excluding basic/process design and automation design is in the scope of EFK.
Architectural design
Mechanical engineering and design
Civil/Structural engineering and design
Piping design
Electrical engineering and design
Infrastructural design